PRAIRIE CENTRAL LINE SUPPLY LTD
NT-00291 - Supply and Delivery of Splice Kits
Award
Awardee
Supplier Awarded
Address
583 PLINGUET STREET
WINNIPEG, Manitoba, R2J 0G3
Canada
Awarded Value
$38,962.00
Award Date
2022/10/11 01:00:00 AM EDT
Description
Underground cable required immediate replacement. The required splices for the temporary replacement on the line are not carried in stores. The standard delivery time for these splices
is 9-weeks. Construction was in contact with 3M to advance the delivery however an earlier deliver could not be guaranteed. To reduce the duration of an outage risk, construction reached out to other utilities to see if the required splices could be acquired sooner. San Diego Gas & Electric was able to provide the required splices
See more
is 9-weeks. Construction was in contact with 3M to advance the delivery however an earlier deliver could not be guaranteed. To reduce the duration of an outage risk, construction reached out to other utilities to see if the required splices could be acquired sooner. San Diego Gas & Electric was able to provide the required splices
We use cookies and other similar technology to deliver our online services. Essential cookies are used to enable you to access and navigate our site. These are necessary and are always on. We also use functional, analytics, and marketing cookies when we have your consent to do so. For more information on how we use cookies, please consult our Privacy Policy.